IBM Tivoli Monitoring V6.3 Implementation — Question 5

A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order.
Which option will group the tasks?

Answer options

Correct answer: A

Explanation

The correct answer is A because selecting the task work orders and creating a Work Package effectively groups the remaining tasks under a new parent work order. Options B, C, and D do not provide the correct method for grouping the tasks as required.