IBM Tivoli Monitoring V6.3 Implementation — Question 23

A company recently had to do a massive overhaul of a pump asset. The planner has to enter hundreds of tasks, sequence those tasks, and identify the labor, material, services and tools used on each task.
The planner knows that this work will occur again as the company has numerous pumps of the same type.
What must the planner do so that the work plan does not have to be re-entered?

Answer options

Correct answer: A

Explanation

The correct answer is A, as creating a Job Plan allows the planner to save and reuse the detailed work plan for similar tasks in the future. Options B and C do not address the need for reusing the work plan, and D, while related, is not the best choice as it implies using a specific functionality rather than the broader concept of developing a Job Plan.