IBM MQ v9.2 System Administration — Question 42

In which status can a Job Plan be modified to add a new task?

Answer options

Correct answer: D

Explanation

A Job Plan can only be modified to add tasks when it is in the PNDREV (Pending Review) status, as this indicates that it is not yet finalized. In contrast, the NEW status is for initial creation, REVISED is for edits after approval, and INACTIVE means the Job Plan is not currently in use, preventing any modifications.