In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?
Answer options
- A. the Job Plan finish date
- B. the PM target finish date
- C. the Work Order target start date + the Job Plan duration
- D. the Job Plan start date + the Job Plan duration
Correct answer: C
Explanation
The correct answer is C, as the target finish date for a Work Order is derived by adding the Job Plan duration to the Work Order target start date. The other options do not accurately reflect how the target finish date is computed within the Work Order Tracking application.