Certified Information Privacy Technologist (CIPT) — Question 179
Which of the following is NOT a step in the methodology of a privacy risk framework?
Answer options
- A. Assessment
- B. Monitoring
- C. Response
- D. Ranking
Correct answer: D
Explanation
The correct answer is D, as 'Ranking' is not typically included in the standard steps of a privacy risk framework methodology. The other options, Assessment, Monitoring, and Response, are all integral parts of managing privacy risks effectively.