Huawei Certified ICT Expert – Routing and Switching (HCIE-RS) — Question 42
Which of the following operations is not involved in the middle phase of a migration?
Answer options
- A. Service test
- B. Migration preparation
- C. On-site monitoring
- D. Migration implementation
Correct answer: C
Explanation
The correct answer is C, as on-site monitoring is typically part of the final phase of migration to ensure everything is functioning properly. The other options, including service testing, migration preparation, and migration implementation, are essential components of the middle phase of migration.