Google Cloud Digital Leader — Question 92
A public cloud provider's service level performance has moved below the service level objective (SLO), but remains above the service level agreement (SLA).
What is an outcome of this change in service level performance?
Answer options
- A. The public cloud provider is encouraged to push out new updates
- B. The public cloud provider is encouraged to prioritize service reliability
- C. End users face unexpected or prolonged downtime
- D. End users face a decrease in service latency
Correct answer: B
Explanation
The correct answer is B because a drop in performance below the SLO signals the need for the provider to enhance reliability to meet customer expectations. Option A is incorrect as prioritizing updates may not directly address the reliability issue, while C and D are wrong since they address user experiences that may not necessarily follow from the performance being above the SLA.