GIAC Certified Project Manager (GCPM) — Question 4
Which of the following techniques is described in the statement below?
"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid of any resource limitations by performing a forward and backward pass analysis through the schedule network."
Answer options
- A. Resource utilization
- B. Critical Chain method
- C. Resource leveling heuristic
- D. Critical path method
Correct answer: C
Explanation
The correct answer, Resource leveling heuristic, focuses on adjusting the start and finish dates of tasks to address resource constraints while maintaining the project schedule. The Critical path method, on the other hand, identifies the longest path through the project and does not involve resource limitations. Resource utilization and Critical Chain method also differ as they pertain to managing resources and time buffers rather than specifically leveling resources.