Certified Scrum Master (CSM) – GAQM — Question 78

What does the Sprint Backlog consist of?

Answer options

Correct answer: C

Explanation

The correct answer is C because the Sprint Backlog is made up of selected items from the product backlog along with the tasks necessary to complete those items during the sprint. Options A, B, and D are incorrect as they do not encompass the complete set of components found in the Sprint Backlog.