Certified Scrum Master (CSM) – GAQM — Question 78
What does the Sprint Backlog consist of?
Answer options
- A. User Stories, only.
- B. Use Cases
- C. Selected Backlog Items and Tasks
- D. Test cases
Correct answer: C
Explanation
The correct answer is C because the Sprint Backlog is made up of selected items from the product backlog along with the tasks necessary to complete those items during the sprint. Options A, B, and D are incorrect as they do not encompass the complete set of components found in the Sprint Backlog.