Certified Scrum Master (CSM) – GAQM — Question 63
What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?
Answer options
- A. By ensuring the meetings start and end at the proper time
- B. By facilitating Development Team decisions and removing impediments
- C. By preventing changes to the Backlog once the Sprint begins
- D. By keeping high value features high in the Product Backlog
Correct answer: B
Explanation
The correct answer is B because a Scrum Master’s role is to facilitate decisions made by the Development Team and to remove any barriers that might hinder their work. Options A, C, and D, while important, do not directly address the Scrum Master's primary responsibility of ensuring the team can work effectively by resolving impediments.