Certified Scrum Master (CSM) – GAQM — Question 61

The Sprint Backlog is owned by?

Answer options

Correct answer: C

Explanation

The Development Team is responsible for the Sprint Backlog as it reflects their work and commitments for the sprint. The Scrum Master and Product Owner support the team but do not own the backlog themselves, making option C the correct choice.