Certified Scrum Master (CSM) – GAQM — Question 52
The correct sequence of events in using Scrum framework is as follows:
Answer options
- A. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- B. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
- C. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- D. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective
Correct answer: B
Explanation
The correct sequence begins with Sprint Planning, followed by the Sprint itself, then Daily Scrum, Sprint Review, and finally Sprint Retrospective, as outlined in option B. Options A, C, and D misplace the Daily Scrum and Sprint Review in relation to the Sprint Retrospective, which disrupts the intended flow of Scrum practices.