Certified Scrum Master (CSM) – GAQM — Question 52

The correct sequence of events in using Scrum framework is as follows:

Answer options

Correct answer: B

Explanation

The correct sequence begins with Sprint Planning, followed by the Sprint itself, then Daily Scrum, Sprint Review, and finally Sprint Retrospective, as outlined in option B. Options A, C, and D misplace the Daily Scrum and Sprint Review in relation to the Sprint Retrospective, which disrupts the intended flow of Scrum practices.