Certified Scrum Master (CSM) – GAQM — Question 46

_____________ can change the priority of items in the _________ backlog at any time.

Answer options

Correct answer: C

Explanation

The correct answer is C because the Product Owner is responsible for managing the product backlog and can adjust priorities as necessary. Options A and D are incorrect since the Team and Scrum Master do not have the authority to prioritize backlog items. Option B is wrong as it refers to the Sprint backlog, which is not the focus of this question.