Certified Scrum Master (CSM) – GAQM — Question 40

Which of the following is not reflected in a Sprint Burn down Chart?

Answer options

Correct answer: B

Explanation

The correct answer is B, as a Sprint Burn down Chart typically tracks the total work remaining, not the number of tasks. Options A, C, and D are all elements that are represented in the chart, providing insights into the progress of the sprint.