Certified Scrum Master (CSM) – GAQM — Question 4
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
Answer options
- A. The development team cannot meet their Sprint commitment to complete work if requirements are changing
- B. A Sprint cycle is not enough time for senior management review and approve changes
- C. This forces Product Owners to focus on what is really important for the team to develop.
- D. The development team must be able to limit the Product Owner authority
Correct answer: C
Explanation
The correct answer is C because it emphasizes the need for Product Owners to prioritize effectively, ensuring that the team is focused on delivering the most valuable work. Option A is incorrect as it relates to commitment but doesn't highlight the importance of prioritization. Option B suggests a timing issue related to management that isn't the core reason, and option D misinterprets the collaborative nature of Scrum, which does not aim to limit authority but to streamline focus.