Certified Scrum Master (CSM) – GAQM — Question 38

Which of the following is reflected in a Sprint Burn down Chart?

Answer options

Correct answer: D

Explanation

The correct answer is D because a Sprint Burn down Chart tracks the amount of work remaining in terms of work hours throughout the sprint. Options A, B, and C do not accurately represent what is shown in the chart, as it does not include team members' names or counts of backlog items or tasks.