Certified Scrum Master (CSM) – GAQM — Question 38
Which of the following is reflected in a Sprint Burn down Chart?
Answer options
- A. Team Members Name
- B. Number of Product Backlog Items Completed
- C. Number of Tasks Remaining
- D. Work Hours Remaining
Correct answer: D
Explanation
The correct answer is D because a Sprint Burn down Chart tracks the amount of work remaining in terms of work hours throughout the sprint. Options A, B, and C do not accurately represent what is shown in the chart, as it does not include team members' names or counts of backlog items or tasks.