Certified Scrum Master (CSM) – GAQM — Question 23
Which of the following statements best describes Product Backlog items?
Answer options
- A. Undefined or poorly defined Product Backlog items should be placed on the Product Backlog with a low priority
- B. All Product Backlog items are the result of a(n) analysis, requirements and/or design phase(s).
- C. Undefined or poorly defined Product Backlog items should be kept out from the Product Backlog until sufficient detail is known.
- D. Every Product Backlog item, whether low priority or high priority, should possess sufficient detail for the Team to complete in a Sprint.
Correct answer: C
Explanation
The correct answer, C, highlights the importance of having sufficient detail for Product Backlog items before they are added to ensure effective planning and execution. Option A suggests low-priority placement, which does not address the need for clarity. Option B inaccurately implies that all items must come from a formal phase, while D mandates detail for all items, which is impractical for those not yet defined.