Certified Scrum Master (CSM) – GAQM — Question 14
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
Answer options
- A. User Stories
- B. Use cases
- C. Line items
- D. Tasks
Correct answer: D
Explanation
The correct answer is D, as 'Tasks' refer to the individual pieces of work needed to develop a software component. User Stories (A) and Use cases (B) describe requirements and scenarios, while Line items (C) typically refer to entries in a list rather than specific actions needed for development.