Certified Scrum Master (CSM) – GAQM — Question 12
How should items in the Product Backlog be ordered?
Answer options
- A. Alphabetically first and then by list order in the Product Backlog
- B. Grouped by business features first and then chronologically by date of original business request
- C. Prioritized by business importance first. The items that result in biggest ROI, must be priorized first
- D. Chronologically by date of original business request first and then by list order in the Product Backlog
Correct answer: C
Explanation
The correct answer, C, emphasizes prioritizing items based on their business importance, ensuring that those with the highest return on investment are addressed first. Options A and D do not focus on business value, while B prioritizes features and dates rather than ROI, making them less effective for backlog arrangement.