EXIN MSP Foundation (Managing Successful Programmes) — Question 2
Which process checks that a programme is worth the time and resources needed to plan the programme?
Answer options
- A. Deliver the capabilities
- B. Embed the outcomes
- C. Evaluate new information
- D. Identify the programme
Correct answer: C
Explanation
The correct answer, C, refers to the process of evaluating new information to determine the feasibility and value of a program before committing resources. The other options do not specifically address the assessment of worthiness in terms of time and resources; they focus on delivering capabilities, embedding outcomes, and identifying the program itself.