Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?
Answer options
- A. The Product Owner
- B. The Scrum Master
- C. The team
Correct answer: C
Explanation
The team is responsible for making the commitment regarding what will be delivered at the end of the Sprint, as they are the ones executing the work. The Product Owner provides the vision and prioritizes the backlog, while the Scrum Master facilitates the process but does not make commitments on behalf of the team.