What is the usual length of the time box for the complete Sprint Planning meeting?
Answer options
- A. Four hours for a 30 day Sprint, one to two hours for a shorter Sprint.
- B. However long it takes to complete the Sprint Backlog.
- C. Never more than two hours, regardless of Sprint length.
Correct answer: A
Explanation
The correct answer is A because it specifies the typical time allocation for Sprint Planning, which is indeed four hours for a 30-day Sprint and proportionally less for shorter Sprints. Option B is incorrect as it suggests an open-ended duration, which is not aligned with Scrum guidelines. Option C is also wrong because it implies a maximum time limit that does not consider the length of the Sprint.