EXIN Agile Scrum Master — Question 9

Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other
Stories.
How should you address this?

Answer options

Correct answer: A

Explanation

The correct approach is to complete the incomplete Stories to ensure that the team's efforts are focused on delivering value within the Sprint. Increasing or re-estimating Velocity or switching to Ideal days does not directly address the issue of the current Sprint's Story completion, while re-estimating all small Stories may not be necessary if the focus should be on finishing the existing ones.