EXIN Agile Scrum Master — Question 9
Your team uses Story Points to estimate User stories.
Halfway through a Sprint, you are not seeing the progress you expected. The Team feels some Stories are not estimated correctly, when compared to other
Stories.
How should you address this?
Answer options
- A. Complete incomplete Stories
- B. Increase or re-estimate Velocity
- C. Re-estimate all small Stories
- D. Switch to using Ideal days
Correct answer: A
Explanation
The correct approach is to complete the incomplete Stories to ensure that the team's efforts are focused on delivering value within the Sprint. Increasing or re-estimating Velocity or switching to Ideal days does not directly address the issue of the current Sprint's Story completion, while re-estimating all small Stories may not be necessary if the focus should be on finishing the existing ones.