EXIN Agile Scrum Master — Question 33

After the creation of the Release Plan, the Product Owner says:
The Scrum Master argues that the end date of the release can be positively or negatively impacted by three factors. Completed work is the first factor.
What are the other two factors?

Answer options

Correct answer: B

Explanation

The correct answer is B because changed requirements directly influence the scope of work and revised estimates reflect the new understanding of the project's progress. The other options either use incorrect terms, such as 'fixed requirements' which imply no changes, or 'estimation mode' which is not relevant in this context.