EXIN Agile Scrum Master — Question 30
Inexperienced Agile teams tend to overestimate how much they will achieve in the first Sprint.
Which project management activity will be most important in this case?
Answer options
- A. Determine the Velocity of the Team and plan accordingly
- B. Use Planning Poker to get a reliable estimate
- C. Use Stakeholder Management to manage expectations
Correct answer: C
Explanation
The correct answer is C because managing stakeholder expectations is vital when a team is overestimating their capabilities. While determining velocity and using Planning Poker can be beneficial, they do not directly address the misalignment between team output and stakeholder expectations, which is critical for ensuring satisfaction and clarity.