EXIN Agile Scrum Master — Question 19
Your company wants to be highly responsive to bug reports or feature requests from your customers. For your customers it is more important to have confidence in the date by which you promise to have a fix than an occasional quick fix.
What part of Scrum allows you to have this predictability?
Answer options
- A. Agile planning
- B. The Velocity of the Team
- C. Working in strict timeboxes
Correct answer: C
Explanation
Working in strict timeboxes, such as sprints, allows teams to deliver features and fixes within a set timeframe, providing predictability to stakeholders. While Agile planning and team velocity are important, they do not inherently guarantee the timeliness that strict timeboxes ensure. Therefore, option C is the best choice for establishing predictability in delivery.