EXIN Agile Scrum Foundation — Question 7

Who should update the work estimates during the Sprint?

Answer options

Correct answer: A

Explanation

The correct answer is A, as only the team members who are actively involved in the work have the insight needed to provide accurate updates on work estimates. The Project Manager and Product Owner are not directly involved in the execution of tasks and may not have the most current understanding of the team's progress and challenges.