EXIN Agile Scrum Foundation — Question 52
A Definition of Done contains a number of characteristics of the potentially releasable Increment.
Which of the following characteristics belong in the Definition of Done?
Answer options
- A. Functional Requirement
- B. Length of the Time-Box
- C. Organizational Processes
- D. Velocity of the Team
Correct answer: C
Explanation
The correct answer is C, as Organizational Processes are essential for ensuring that all aspects of work meet the defined criteria for being considered complete. Options A, B, and D do not directly pertain to the criteria that define when an Increment is releasable.