EXIN Agile Scrum Foundation — Question 47
During the Daily Scrum three questions are answered.
Which question is one of these questions?
Answer options
- A. What has been accomplished since the last meeting?
- B. Who should take on the next task?
- C. Which requests of the customer did we receive?
Correct answer: A
Explanation
The correct answer is A, as the Daily Scrum focuses on progress made since the last meeting. Options B and C do not align with the purpose of the Daily Scrum, which is to discuss accomplishments and impediments rather than task assignments or customer requests.