EXIN Agile Scrum Foundation — Question 44
A project is so large, that it requires multiple Scrum Teams to work on it. The Scrum Teams will be working in 2 different locations.
Who would lead the Sprint Planning meetings?
Answer options
- A. One of the Scrum Teams should lead the Sprint Planning meeting.
- B. The Scrum Manager should lead the Sprint Planning meeting.
- C. Each Scrum Team should lead their own Sprint Planning meeting.
Correct answer: C
Explanation
The correct answer is C because each Scrum Team is responsible for planning their own work during the Sprint, which allows them to tailor their meetings to their specific needs. Option A is incorrect as only one team leading would not accommodate the needs of all teams. Option B is also wrong since the Scrum Manager does not lead the Sprint Planning; it's up to the individual teams to plan their Sprints.