EXIN Agile Scrum Foundation — Question 42
Suppose that you track the Sprint progress in a Burn-Down chart. You have added an extra line to show the planned progress. The line of the actual progress stays below the planning line.
What does this say about the progress?
Answer options
- A. You are ahead of schedule.
- B. You are behind schedule.
- C. You have not planned well.
Correct answer: A
Explanation
The correct answer is A because if the actual progress line is below the planned line, it indicates that tasks are being completed faster than anticipated, meaning the team is ahead of schedule. Options B and C are incorrect as they would suggest being behind schedule or poor planning, which is not the case here.