Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?
Answer options
- A. The Product Owner
- B. The Scrum Master
- C. The team
Correct answer: C
Explanation
The commitment on what will be delivered at the end of the Sprint is made by the team, as they are the ones who will actually carry out the work. The Product Owner defines the priorities and the Scrum Master facilitates the process, but it is ultimately the team that commits to the work they can complete within the Sprint timeframe.