EXIN Agile Scrum Foundation — Question 25
How should 'done' be defined when multiple teams are working on a single product?
Answer options
- A. All teams must have the same definition of 'done'.
- B. Each team must define and use their own definition of 'done'.
- C. The Scrum Master defines when the item is 'done'.
Correct answer: A
Explanation
The correct answer is A because having a unified definition of 'done' ensures consistency and clarity across all teams, which is crucial for collaboration. Option B could lead to discrepancies and misunderstandings, while option C incorrectly centralizes the definition to the Scrum Master, neglecting the collaborative nature of the teams.