EXIN Agile Scrum Foundation — Question 23
Which statement describes Release Planning?
Answer options
- A. After looking at all the stories in the backlog, the team estimates their effort in detail.
- B. The team meets with the customer to negotiate the scope, cost and time of the release.
- C. The team and the Product Owner agree on an initial plan for the delivery of features.
Correct answer: C
Explanation
The correct answer, C, highlights the collaboration between the team and the Product Owner in formulating a delivery plan for the features. Option A, while discussing effort estimation, does not encompass the planning aspect, and option B focuses on negotiations rather than the agreement on a plan.