EXIN Agile Scrum Foundation — Question 18

For a Sprint, progress is monitored in a burn-up chart with bars.
What makes the bar become longer?

Answer options

Correct answer: C

Explanation

The correct answer is C, as removing work from the Sprint Backlog directly increases the remaining work completed in the burn-up chart, which causes the bar to grow longer. Option A is incorrect because the passage of time alone does not affect the length of the bar. Option B is also incorrect since adding work would not lengthen the bar, but instead, potentially shorten the remaining work completed.