EXIN Agile Scrum Foundation — Question 18
For a Sprint, progress is monitored in a burn-up chart with bars.
What makes the bar become longer?
Answer options
- A. The progression of time.
- B. Work is added to the Sprint Backlog.
- C. Work is deleted from the Sprint Backlog.
Correct answer: C
Explanation
The correct answer is C, as removing work from the Sprint Backlog directly increases the remaining work completed in the burn-up chart, which causes the bar to grow longer. Option A is incorrect because the passage of time alone does not affect the length of the bar. Option B is also incorrect since adding work would not lengthen the bar, but instead, potentially shorten the remaining work completed.