EXIN Agile Scrum Foundation — Question 11
Who is responsible for implementing the actions agreed upon by the team during a Retrospective?
Answer options
- A. The Product Owner
- B. The Scrum Master
- C. The team
Correct answer: C
Explanation
The team is responsible for implementing the actions decided upon during the Retrospective as they are the ones who collectively assess their work and identify improvements. The Product Owner and Scrum Master may facilitate the process, but they do not execute the agreed actions themselves.