Certified Chief Information Security Officer (CCISO) — Question 87

Which of the following activities results in change requests?

Answer options

Correct answer: C

Explanation

Preventive actions are intended to avert potential issues in the future, which can lead to formal change requests to the project plan. In contrast, corrective actions and defect repairs address existing problems, while inspection is a review process that does not typically result in change requests.