Which of the following is considered a project versus a managed process?
Answer options
- A. ongoing risk assessment of routine operations
- B. continuous vulnerability assessment and vulnerability repair
- C. monitoring external and internal environment during incident response
- D. installation of a new firewall system
Correct answer: D
Explanation
The installation of a new firewall system is a distinct project with a defined beginning and end, making it a project. In contrast, the other options describe ongoing processes that are part of continuous operations and management rather than finite projects.