While designing a secondary data center for your company what document needs to be analyzed to determine to how much should be spent on building the data center?
Answer options
- A. Business continuity plan
- B. Application mapping document
- C. Disaster recovery strategic plan
- D. Enterprise Risk Assessment
Correct answer: C
Explanation
The Disaster recovery strategic plan outlines the necessary expenditures and priorities for creating a secondary data center to ensure business continuity during disruptions. The other documents, while important, do not specifically address budget allocation for establishing a new data center.