Certified Threat Intelligence Analyst (CTIA) — Question 37
What is the correct sequence of steps involved in scheduling a threat intelligence program?
1. Review the project charter
2. Identify all deliverables
3. Identify the sequence of activities
4. Identify task dependencies
5. Develop the final schedule
6. Estimate duration of each activity
7. Identify and estimate resources for all activities
8. Define all activities
9. Build a work breakdown structure (WBS)
Answer options
- A. 1-->9-->2-->8-->3-->7-->4-->6-->5
- B. 3-->4-->5-->2-->1-->9-->8-->7-->6
- C. 1-->2-->3-->4-->5-->6-->9-->8-->7
- D. 1-->2-->3-->4-->5-->6-->7-->8-->9
Correct answer: A
Explanation
Option A is correct because it follows the logical steps of project management, starting with reviewing the project charter and culminating in the final schedule after all tasks and resources are accounted for. The other options either rearrange the steps incorrectly or miss important sequencing, which can lead to gaps in the project planning process.