Chris is a senior network administrator. Chris wants to measure the Key Risk Indicator (KRI) to assess the organization. Why is Chris calculating the KRI for his organization? It helps Chris to:
Answer options
- A. Identifies adverse events
- B. Facilitates backward viewing
- C. Notifies when risk has reached threshold levels
- D. Facilitates post incident management
Correct answer: C
Explanation
The correct answer, C, is right because KRIs are specifically designed to signal when risk levels have crossed established thresholds, allowing for proactive management. Option A is incorrect as it refers to identifying events rather than measuring risk. Option B does not apply here since KRI focuses on forward-looking risk, and D is not relevant as it pertains to managing incidents after they occur.