Dell EMC Specialist – Systems Administrator, ECS — Question 38
An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?
Answer options
- A. Service laptop must be on the same IP network as the iDRACs
- B. At least 36 in (92 cm) clearance exists in front of and behind the cabinet
- C. Power distribution must support the power rating of a single node
- D. Single power zone must be used with adequate power cables
Correct answer: C
Explanation
The correct answer is C because ensuring that the power distribution can handle the power rating of a single node is crucial for the system's stability. Options A and B, while important, are not directly related to the hardware installation verification. Option D is also relevant but does not address the specific requirement for power ratings.