Dell EMC Specialist – Systems Administrator, ECS — Question 3
A VxRail D560 cluster was delivered six months ago and now needs to be prepared for installation with the target code. What is the correct method to complete the task?
Answer options
- A. Boot into RASR ISO and perform a RASR Reset
- B. Boot into RASR USB and perform a RASR Reset
- C. Boot into SD card and perform a Factory Reset
- D. Boot into RASR ISO and perform a Factory Reset
Correct answer: A
Explanation
The correct answer is A because using the RASR ISO to perform a RASR Reset is the appropriate method for preparing the cluster for installation. The other options either involve incorrect media (USB or SD card) or inappropriate reset types (Factory Reset) that do not align with the requirements for installation preparation.