How does the Network Validation Tool (NVT) validate Top of Rack (ToR) switch configurations?
Answer options
- A. NVT requires switch logon information and parses through the running-config of the switch
- B. Using the switch grab batch file, the output is imported into the NVT User Interface
- C. The running-config is imported into the NVT User Interface
- D. Top of Rack switches are always manually validated prior to implementation
Correct answer: A
Explanation
The correct answer is A because the NVT relies on access to the switch's running-config to perform its validation. Option B is incorrect as it describes a different process that does not directly validate configurations. Option C lacks the necessary authentication step, and option D is incorrect as it suggests a manual process which the NVT aims to automate.