Dell EMC Specialist – Implementation Engineer, vSAN Ready Nodes — Question 22
What does the data import session Pause operation do?
Answer options
- A. Deactivates the host to PowerStore control path
- B. Stops the source to PowerStore background copy operation
- C. Stops the source to PowerStore cutover operation
- D. Deactivates the host to PowerStore data path
Correct answer: B
Explanation
The correct answer is B because the Pause operation specifically halts the background copy process from the source to PowerStore, allowing for adjustments or troubleshooting. Options A and D refer to deactivating host paths, which are not related to the import session's copying activities, while option C involves the cutover operation, which is separate from the background copy process.