Dell EMC Specialist – Implementation Engineer, vSAN Ready Nodes — Question 10
How is the upgrade process on a multi-appliance cluster run?
Answer options
- A. Master appliance primary node first, then the peer node
- B. On one node at a time
- C. On all primary nodes first, then peer nodes
- D. In parallel on all nodes
Correct answer: A
Explanation
The correct answer is A because the upgrade process starts with the master appliance's primary node to ensure stability, followed by the peer node. Options B, C, and D are incorrect as they do not reflect the recommended upgrade sequence which prioritizes the master appliance for a smooth transition.