Dell EMC Associate – Backup and Recovery Solutions Design v2 — Question 23
A customer has created a change management window to perform scheduled system maintenance. During the scheduled downtime window, information will be transferred to another system to ensure continuous availability. What is this process an example of?
Answer options
- A. Data governance
- B. Data migration
- C. Automated failback
- D. Disaster recovery
Correct answer: A
Explanation
The correct answer is A, Data governance, as it involves the overall management of data availability, usability, integrity, and security during the maintenance process. The other options are incorrect because Data migration refers to the actual transfer of data, Automated failback relates to restoring services after a failure, and Disaster recovery is about restoring systems after a major failure, not scheduled maintenance.