What are the considerations when designing a disaster recovery plan based on RTO and RPO?
Answer options
- A. Lower RTO and RPO have no effect on cost
- B. Lower RTO and RPO simplify the solution
- C. Lower RTO and RPO decrease the cost
- D. Lower RTO and RPO increase the cost
Correct answer: D
Explanation
The correct answer is D because lower RTO (Recovery Time Objective) and RPO (Recovery Point Objective) typically require more resources and investments in technology, which results in higher costs. Options A, B, and C are incorrect because they misrepresent the relationship between RTO/RPO and associated costs.