Dell Technologies Proven Professional – PowerStore — Question 4

At what point in the configuration of an External Storage import session does the data path from the host to the PowerStore system become the active I/O path?

Answer options

Correct answer: A

Explanation

The data path becomes the active I/O path at the start of the import session, which is when the configuration is fully engaged. The other options refer to events that happen either prior to or concurrently with the import session but do not activate the I/O path.