Certified CMMC Professional (CCP) — Question 18
CA.L2-3.12.2: Plan of Action defines the clear goal or objective for the plan. What information is generally NOT a part of a plan of action?
Answer options
- A. Completion dates
- B. Milestones to measure progress
- C. Ownership of who is accountable for ensuring plan performance
- D. Budget requirements to implement the plan’s remediation actions
Correct answer: D
Explanation
The correct answer is D because budget requirements are typically not a fundamental component of a Plan of Action, which focuses more on goals, accountability, and progress tracking. Options A, B, and C are all critical elements that help ensure the plan's effectiveness and track its success.